CapeCodFD.com
SANDWICH
PUBLIC SAFETY
CONSTRUCTION PROJECTS
FIRE STATIONS 2 & 3
Updated November 4, 2019
| Fire Station Plan | Latest Update | Construction Progress | Preparation | Planning | Older Facility |
East Sandwich Station 2 - Renovated & Opened June 3, 2018
Forestdale Station 3 - New Station Opened Sept 2019
Sandwich Police - New Station Opened June-July 2019
| Fire Station Plan | Latest Update | Construction Progress | Preparation | Planning | Older Facility |
SANDWICH POLICE & FIRE STATIONS PROJECTS The East Sandwich Fire Station 2 was completed and occupied on June 3, 2018. Three personnel are assigned per shift staffing Engine 2 (452), Breaker 2 (462), and Ambulance 2. A car is also assigned to the station. Work also began at Quaker Meeting House Road & Quaker Road in September 2017 with a large area being cleared and prepared for two structures to be built, including the police station and new Station 3. The new Forestdale Fire Station 3 and the new Sandwich Police Station began to rise in the Spring of 2018. After a number of challenges and changes, the Fire station plan was modified to include "Headquarters" offices, as well as the originally planned space. This made it possible for the Fire Chief, Deputy, Fire Prevention, and EMS officers to have appropriate space within the new station. The new Police Station was the first to be completed and occupied in the Summer of 2019. The modern facility includes the Public Safety Communications Center for both Police and Fire/EMS. The new "Fire Headquarters" at Station 3 was occupied by crews at the end of August 2019. The old Station 3 on Route 130 was closed (although still retained for some storage, at least initially) and apparatus was reassigned. The Shift Commander was moved from downtown Station 1 to Station 3. Apparatus changes, including a Quint Ladder on order, will be assigned once all are delivered and in service. A dedication ceremony for both the new Police Station and Station 3 was held at both stations on September 27, 2019.
|
Police and Fire Stations Approved
SANDWICH VOTERS APPROVED
STATIONS
Sandwich has needed to upgrade its emergency services facilities for
decades.
The police station and 3 fire stations are all inadequate having
been built in
the 1970s. A proposal to build a new Police and Fire
Headquarters station
and build a new fire sub station was rejected in 2013.
The town went back to the
drawing board.
On May 2, 2016 voters approved funding to move forward with a new
Police
Station at Cotuit Road & Quaker Meetinghouse Road.
They also approved building
a new fire station on that site to replace the
1970s Forestdale Fire Station 3 which is currently on Route 130.
While no funds were approved
for headquarters on Route 6A downtown,
funding was approved to make the East Sandwich Fire Station 2 ready
for staffing. It was built in the early 1970s as essentially a
garage with
no living quarters of facilities for staffing.
STATION 3
The Fire Sub Station being built in Forestdale at Quaker Meetinghouse Road &
Cotuit Road.
Architect's drawing.
POLICE STATION
The new Sandwich Police Station architects image.
Sandwich Police & Fire Station 3 Dedication
SANDWICH STATION 3 OPEN HOUSE OCT 2019
| Fire Station Plan | Latest Update | Construction Progress | Preparation | Planning | Older Facility |
FORESTDALE - FIRE STATION 3
UPDATE: Photos October 26, 2019
The Sandwich FD held an Open House at the new Sandwich Station 3 in Forestdale
on October 26, 2019.
| Fire Station Plan | Latest Update | Construction Progress | Preparation | Planning | Older Facility |
FIRE STATION 3
UPDATE: Photos September 27, 2019
Sandwich Fire Headquarters Station 3
The new Forestdale Fire Station was opened in September 2019.
The dedication ceremony was held on September 27, 2019.
Fire Chief John "JJ" Burke prepares to cut the red ribbon
with three of his predecessors at the new Sandwich Station 3.
Sandwich Fire Chief John "JJ" Burke
Fire station conference room
Fire department day room - living room at new station.
Day room and kitchen
Kitchen in the new station.
Fire Prevention office
Bunk rooms include lockers and sleeping for 2 personnel.
The apparatus floor is two bays, double deep, with a single bay for a command vehicle
UPDATE: Photos August 5, 2019
SANDWICH FIRE STATION 3
The new Sandwich "sub station" is located across the driveway from the police
station
at 251 Cotuit Road, Forestdale. The 2-1/2 bay, drive thru, steel building will
also house
the headquarters administrative offices of the Fire Chief, Deputy Chief, Fire
Inspector,
and EMS Officer, in addition to the shift commander and crew.
The station is expected to be in operation by the end of
August 2019.
The plan calls for the new Quint (on order), the Squad 4 engine, a forestry
unit,
an ambulance, and the shift command car to be assigned to this station.
Photos August 5, 2019
Three doors to the north
Two doors to the south.
Kitchen and day room.
Protective clothing racks leading to apparatus floor.
The southwest corner of the station. The ambulance is expected to run out of this side.
The north side of the station will house fire apparatus
UPDATE: Photos July 9, 2019
Sandwich Public Safety Complex
July 9, 2019
Fire station behind police station.
UPDATE: Photos May 7, 2019
Sandwich Fire Department's new Station 3 is coming along.
May 7, 2019
UPDATE: Photos April 24, 2019
Sandwich Station 3
Construction continued over the winter.
April 24, 2019
UPDATE: Photos January 15, 2019
The future Sandwich Station 3 in Forestdale
Will house headquarters offices when opened
January 15, 2019
UPDATE: Photos January 4, 2019
Sandwich Station 3
Route 130
January 4, 2019
UPDATE: Photos December 31, 2018
Future Station 3
December 31, 2018
UPDATE: Photos December 13, 2018
Station 3 Construction
December 13, 2018
UPDATE: Photos November 7, 2018
Sandwich Police Station and Fire Station 3
Nov 7, 2018
Fire Station
Nov 7, 2018
UPDATE: Photos October 25, 2018
Sandwich Station 3 Construction
to the right of the new Sandwich Police Station under construction.
October 25, 2018
STATION 3 & POLICE STATION
UPDATE: Photos September 18, 2018
Sandwich Station 3 Construction
to the right of the new Sandwich Police Station under construction.
September 18, 2018
UPDATE: Photos August 23, 2018
The future Fire Station 3 in Forestdale taking shape August 23, 2018.
UPDATE: Photos July 31, 2018
New Forestdale Fire Station in background.
UPDATE: Photos April 20, 2018
Forestdale combination Police & Fire Station 3
April 20, 2018
UPDATE: Photos December 30, 2017
Forestdale combination Police & Fire Station 3
December 30, 2017
UPDATE: Photos September 8, 2017
Photos September 8, 2017
Cotuit Road & Quaker Meetinghouse
Future Station 3 / Fire & Police HQ
Present Sandwich Station 3
March 2017 photo
-----------------------
EAST SANDWICH STATION 2
STATION 2 OPEN
UPDATE: Photos Nov 7, 2018
East Sandwich Station 2
Full glass doors
Nov 7, 2018
STATION 2 OPENED
UPDATE: Photos June 3, 2018
(OPENED)
East Sandwich Station 2
Renovated, opened and staffed
Engine 452 (E-2) - Breaker 462 (B-2) - Ambulance 458 (A-2)
June 3, 2018
UPDATE: Photos April 20, 2018
East Sandwich Station 2
April 20, 2018
UPDATE: Photos December 30, 2017
East Sandwich Station 2
December 30, 2017
UPDATE: Photos September 25, 2017
Photos September 25, 2017
UPDATE: Photos September 7, 2017
East Sandwich Station 2
Closed for renovations
Photos Sept 7, 2017
UPDATE: Photos August 16, 2017
East Sandwich closed prior to
renovations.
Photos Aug 16, 2017
| Fire Station Plan | Latest Update | Construction Progress | Preparation | Planning | Older Facility |
The future police and fire sub station site at Quaker Meeting
House Rd
and Cotuit Road in Forestdale.
| Fire Station Plan | Latest Update | Construction Progress | Preparation | Planning | Older Facility |
Police and Fire Stations Approved
SANDWICH VOTERS APPROVED
STATIONS
Sandwich has needed to upgrade its emergency services facilities for
decades.
The police station and 3 fire stations are all inadequate having
been built in
the 1970s. A proposal to build a new Police and Fire
Headquarters station
and build a new fire sub station was rejected in 2013.
The town went back to the
drawing board.
On May 2, 2016 voters approved funding to move forward with a new
Police
Station at Cotuit Road & Quaker Meetinghouse Road.
They also approved building
a new fire station on that site to replace the
1970s Forestdale Fire Station 3 which is currently on Route 130.
While no funds were approved
for headquarters on Route 6A downtown,
funding was approved to make the East Sandwich Fire Station 2 ready
for staffing. It was built in the early 1970s as essentially a
garage with
no living quarters of facilities for staffing.
East Sandwich Station 2 to be renovated and made inhabitable for staffing.
Forestdale Station 3 to be
replaced by a new station at Cotuit Road &
Quaker Meetinghouse Road with a new Police station. The
station was
first staffed in 1993 as that section of town has grown
considerably.
The combination Fire and
Police Headquarters originally proposed in
2013 which was rejected at the time.
| Fire Station Plan | Latest Update | Construction Progress | Preparation | Planning | Older Facility |
CapeCodFD.com
2018