PLYMOUTH
WEST PLYMOUTH - FIRE STATION 2
(COMPLETED JULY 2024)
(RENOVATION 2023-24)
Updated November 23, 2024
| Fire Station Plan | Latest Update | Construction Progress | Preparation | Planning | Older Facility |
PLYMOUTH FIRE STATION 2 PROJECT The Town of Plymouth has 7 fire stations. In recent years the town has experienced several issues with their fire stations. The oldest fire station built in 1911 at 0 Spooner Street in North Plymouth was replaced with a new North Plymouth Fire Station at 15 Hedge Road in 2020. Before the new station was completed, the old station had to be vacated on Nov 6, 2019 when a portion of the floor failed. Apparatus had to be relocated (E7 to Station 1) until the new station opened on July 13, 2020. About the same time, in October 2019, some long needed roof repairs were being done at the Headquarters Station 1 at 114 Sandwich Street occupied around 1978. The ceiling collapsed and made the station uninhabitable for a period of time. A trailer was located on the station site to support a crew and some apparatus had to be relocated to other stations. Administrative offices were temporarily moved to the Cedarville Station 6 until repairs could be completed. In early 2020, problems were uncovered at the West Plymouth (Seven Hills) Station 2 built in 1975. It was determined that the station needed to have work done on that station as well. A trailer was placed on site for personnel. It was determined that the station needed major renovations of the living space and ultimately the original living space was torn down and is being rebuilt. Some apparatus has been relocated during construction. Looking ahead, a major renovation of the Manomet (Station 5) is also planned and is expected to begin in Summer 2023. Renovation of Station 2 completed and operational in July 2024.
|
|
Planned West Plymouth Station 2 Renovation
PLYMOUTH FIRE STATION 2
West Plymouth
(Renovation 2023-24)
The West Plymouth (Seven hills) Fire Station 2
was opened around 1975.
A major renovation of the station was begun in 2022
with a trailer being placed on site and apparatus moved
to other facilities.
In 2023, the old living quarters was torn down and construction of
the new living quarters began,
| Fire Station Plan | Latest Update | Construction Progress | Preparation | Planning | Older Facility |
UPDATE: Photos October 23, 2024
PLYMOUTH STATION 2
The West Plymouth Fire Station 2, and department and Repair Shops.
Renovation Complete.
October 23, 2024
| Fire Station Plan | Latest Update | Construction Progress | Preparation | Planning | Older Facility |
UPDATE: Photos July 20, 2024
PLYMOUTH STATION 2
The West Plymouth Fire Station 2, and department and Repair Shops.
Renovation Complete. Moved back in.
July 20, 2024
UPDATE: Photos June 20, 2024
PLYMOUTH STATION 2
The West Plymouth Fire Station 2, and department and Repair Shops.
Renovation Complete. Moved back in.
June 20, 2024
UPDATE: Photos April 8, 2024
PLYMOUTH STATION 2
The West Plymouth Fire Station 2, and department and Repair Shops.
Renovation Complete. Moved back in.
April 8, 2024
UPDATE: Photos January 18, 2024
PLYMOUTH STATION 2
The West Plymouth Fire Station 2, and department and Repair Shops,
renovation progress.
January 18, 2024
UPDATE: Photos October 19, 2023
PLYMOUTH STATION 2
The West Plymouth Fire Station 2, and department and Repair Shops,
renovation progress.
October 19, 2023
UPDATE: Photos July 17, 2023
PLYMOUTH STATION 2
The West Plymouth Fire Station 2, and department and Repair Shops,
renovation progress.
July 17, 2023
UPDATE: Photos May 10, 2023
PLYMOUTH STATION 2
The West Plymouth Fire Station 2, and department and Repair Shops, was built
around 1975.
The addition of new living quarters under way.
May 10, 2023
UPDATE: Photos March 6, 2023
PLYMOUTH STATION 2
The West Plymouth Fire Station 2, and department and Repair Shops, was built
around 1975.
The addition of new living quarters under way.
March 6, 2023
Mar 6, 2023
STATION 7 NORTH PLYMOUTH
The North Plymouth Station 7 is expected to open in July.
Paving and final touches are being completed.
| Fire Station Plan |
Latest Update |
Construction Progress |
Preparation | Planning |
Older Facility |
PREPARATION FOR RENOVATIONS
A portable trailer was brought in to the West Plymouth Station to house
firefighters
during the renovation of the living quarters at Station 2.
SEPT 2022
LIVING QUARTERS
The original living quarters in this space will be torn down.
Preparing to tear down the original living space.
One of the apparatus bays was partitioned off to provide for construction space.
| Fire Station Plan | Latest Update | Construction Progress | Preparation | Planning | Older Facility |
MAJOR RENOVATIONS
The entire living quarters of the station will be removed and replaced by a
new 2 story addition.
| Fire Station Plan | Latest Update | Construction Progress | Preparation | Planning | Older Facility |
WEST PLYMOUTH - STATION 2
PLYMOUTH STATION 2
The West Plymouth Fire Station 2, and department and Repair Shops, was built
around 1975.
There are 3 double deep drive through bays which typically house
Engine 2, A Spare Engine, Breaker 172, A Spare Breaker, Tanker 2, and Ambulance
2.
The repair shops with about 3 bays is located on the rear of the building.
2006 Photos
CapeCodFD.com
2023